Slow start after the Thai Holidays. Generator is still in repair but some essential materials have arrived… Solar System, Tiles for the bathroom, Toilets, Sinks and Fans.
Day 327 – 10/04
Mae Hong Son is very dry and hot in March/April. Work has been going slow as the generator keeps breaking down but the workers could install the railing for the stairs and the open space. They will also install it on the balconies and it will be covered with wood. Very happy that the stairs are nearly finished as it makes all the other work logistics in the building easier. Now the workforce is leaving for a ten day Songkran Holiday. After that hopefully things speed up.
Day 323 – 06/04
Day 319 – 02/04
Day 311 – 25/03
Day 303 – 17/03
Day 298 – 12/03
Day 286 – 28/02
Day 279 – 21/02
Day 272 – 14/02
Workers fixed little mistakes here and there, plastering the last bits as well as connecting the pipes between the different floors. Some pipes have been put into place quite randomly so we had to correct position & slope etc. – not so easy but now all at the right place. Waterproof liquid has been used to treat the flat roof for the upcoming cement topping.