Skip to content

MHS Project

Building Updates

Building A Modern Eco-House in Mae Hong Son, Thailand.

More

  • Contact

Recent Posts

  • Finished Build (update)
  • Day 437 – 29/07
  • Day 430 – 22/07
  • Day 425 – 17/07
  • Day 415 – 07/07

Archives

  • July 2020
  • July 2017
  • June 2017
  • May 2017
  • April 2017
  • March 2017
  • February 2017
  • January 2017
  • December 2016
  • November 2016
  • October 2016
  • September 2016
  • August 2016
  • July 2016
  • June 2016
  • May 2016

Month: September 2016

Day 131 – 26/09

Lots of steel bending… now some of the side-beams getting installed.

p16092616590910
s__15015940
s__15015944
s__15015943
s__15015941
s__14876680
Posted on September 26, 2016

Day 125 – 20/09

Metal frames setup complete for the third floor, preparing for the beams and slab… now lots of steel bending ahead.

p16091918114310
s__14786563
s__14557194
s__14557190
s__14786565
s__14786567
Posted on September 20, 2016September 21, 2016

Day 118 – 13/09

Second Floor columns getting poured. Heavy rain for at least 3-4 hours a day but luckily had some quick time to do some pictures from the air.

dji_0012
dji_0022
dji_0004
workers4
workers1
workers3
dji_0025
Posted on September 13, 2016September 19, 2016

Day 115 – 10/09

Slab is done, now moving forward and prepping for the next round of columns to hold the third floor.

p16091017372610

Posted on September 10, 2016September 19, 2016

Day 114 – 09/09

Second Floor Slab nearly done

s__14303252
s__14303250
s__14303253
s__14303248
s__14303249
s__14303251
Posted on September 8, 2016September 19, 2016

Day 110 – 05/09

Second Floor slab moving slowly as some mistakes have been made. Luckily things could be fixed without too much complications.

S__14073871
S__14204968
S__14204969
S__14204970
S__14204971
S__14204975
Posted on September 5, 2016September 9, 2016