Electric team is finishing up the connections to the solar panels as well as the fuse box. They also installed the LED downlights on two floors and the tests work well. Few more lights and fans to be installed and than all of the electric work will be finished.
Day 373 – 26/05
Unfortunately the wind threw off a few packs of tiles which broke so we have to wait for the next delivery from Chiang Mai. The downstairs bathroom is already tiled, without grout finish and toilet & sink installation. Meanwhile all the ceilings have been closed and all interior painted with white primer paint. Workers also fixed some floor toppings & edges.