Wall plastering still in process, meanwhile the workers built up both bathroom walls (red bricks) and embedded door frames. Sand has been transported to the top to prepare the cement topping for the roof around the skylight.
Author: admin
Day 254 – 27/01
Day 245 – 18/01
Day 238 – 11/01
Things move very slow after a week of new years break for the workers. Plastering corners/beams takes quite some time. Workers are attaching aluminum rails to all edges to make them straight. Looks neat but takes time… Meanwhile several building mistakes have been corrected in the pipe/sewage system. Lots of headaches but things move forward now. The electricity workers have laid the main electric grid throughout the house and we got the frames for the entrance door.