Day 238 – 11/01

Things move very slow after a week of new years break for the workers. Plastering corners/beams takes quite some time. Workers are attaching aluminum rails to all edges to make them straight. Looks neat but takes time… Meanwhile several building mistakes have been corrected in the pipe/sewage system. Lots of headaches but things move forward now. The electricity workers have laid the main electric grid throughout the house and we got the frames for the entrance door.

Day 202 – 06/12

Walls are slowly going up on the different floors. The double walls are build from lightweight Q-Con bricks with 10cm width, leaving another 10cm air-gap in the middle for insulation.