Workers are back on site and poured the topping for the floor. It takes a couple steps to finish it as the roof and balcony areas need a slope for rainwater.
Some aluminum cases have been added for the ceiling along the skylight shaft. Chiang Mai order of insulation material arrived as well. Workers are now off for week or so.
Ceiling aluminum cases are finished and the electrical team has been in the house for the last couple of days to wire up the whole building. Only a few tubes and lines left before they are finished. First load of gypsum boards also arrived to cover the ceiling.