Day 196 – 30/11 The workers build a rough scaffolding around the house with Bamboo poles. Now they take off a few days and than begin with the walls.
Day 194 – 28/11 Roof slab is done and has dried. Good timing as 1500 Q-Con light weight bricks arrived on site from Chiang Mai.
Day 181 – 15/11 All beams have been poured and dried… Now preparing wood platforms and steel for the last slab/roof.
Day 174 – 08/11 Workers finished the last steel bending for the side beams holding the roof. Now adding the wood frames for cement pouring.