Base footings all dried and filled up with earth to level it. First side beams for the ground level are getting attached to the columns.
Month: June 2016
Day 34 – 21/06
Day 32 – 19/06
Day 30 – 17/06
Day 28 – 15/06
Day 25 – 12/06
Day 24 – 11/06
Day 20 – 07/06
Day 18 – 05/06
Five out of six steel posts have been completed. Post base is meant to be 0.3 x 0.5 at the base but are a few centimeters short (0.26 x 0.45) on each end, supposedly to make up for cement spacing. Separation between post bands should be 0.15 but the average is around 0.125 which is good. Tomorrow all posts should be finished. Cement to be poured soon.